Bridges
Chestnut Street Bridge
Updated Jan 20, 2026
Key Issues Identified
- Beams have active corrosion. Abutment was repaired in 2019 after bridge was closed to severe deterioration, with a five year warranty
- Piers have widespread spalling, i.e. flaking and chipping with exposed rebar
- Bearings are over-expanded and have active corrosion
Inspection rating
Fair
A Fair rating indicates that while the bridge’s primary structural elements are sound, they may show signs of minor deterioration, section loss, cracking, or spalling, i.e. flaking and chipping.
current ratings
- Deck: 6
- Superstructure: 5
- Substructure: 5
Bridge Overview
Crosses Over:
- Chestnut Street
Year Built: 1963
Bridge Type: Five-Span Steel Bridge
Planned Improvements
- Full replacement with single span over Chestnut Street with concrete beams.
Why it Matters
- Improved safety and mobility
Timeline
- Under construction 2026; completion expected 2028