Floyd Street Bridge Northbound

Updated Jan 20, 2026

Key Issues Identified

  • Deck separating from the beams
  • Beams are expanding into the abutment backwalls, causing damage
  • Abutments have wide cracks and large spalling, i.e. flaking and chipping
  • Bearings are over-expanded and misaligned

Inspection rating

Fair

A Fair rating indicates that while the bridge’s primary structural elements are sound, they may show signs of minor deterioration, section loss, cracking, or spalling, i.e. flaking and chipping.

current ratings

  • Deck: 6
  • Superstructure: 7
  • Substructure: 6

Bridge Overview

Crosses Over:

  • Floyd Street

Year Built: 1963
Bridge Type: Single-Span Steel Bridge

Planned Improvements

  • Deck replacement

Why it Matters

  • Improved safety and mobility

Timeline

  • Under construction 2026; completion expected 2028

Interstate 65 is closed between the Watterson Expressway (I-264) and downtown Louisville (Jefferson Street) through July 31.

Plan ahead and stay informed. 

Sign up for text and email updates.

Download the Waze nav app.

Follow KYTC D5 on Facebook and X.