Preparations/Closures this Weekend in Louisville

Share this article

Two-month closure of five-mile section of I-65 begins Monday, June 1

Drivers can expect work to begin around 7 p.m. on Sunday, May 31 in advance of the planned temporary closure of a five-mile section of I-65 as part of the I-65 Central Corridor project. Contract crews will complete final striping and staging in advance of the closure between the I-65/I-264 interchange and downtown Louisville.

A rolling road closure will begin around 12:01 a.m. on Monday, June 1 to shift traffic to the signed detour. Crews will close northbound and southbound I-65 between the I-65/I-264 interchange and downtown Louisville. Airport access will remain open throughout the process and during the interstate closure.

What to Expect This Summer

Five miles of I-65 will close between the Watterson Expressway (I-264) and downtown Louisville (Jefferson Street) early on Monday, June 1. I-65 is expected to reopen to two lanes of traffic on Saturday, Aug. 1.

A two-mile section of southbound I-65 between University Boulevard and the Watterson Expressway (I-264) is expected to reopen to two lanes of traffic by Wednesday, July 1.

Ramp and Local Street Closures
The Jefferson Street exit (136C) remains open throughout the closure and provides access to downtown Louisville for drivers on southbound I-65.

The Bank Street on-ramp to westbound I-264/I-64 at 37th Street will also be closed June 1 – July 31. A signed detour will take drivers to 35th Street to 34th Street to Vermont Avenue to westbound I-264 at 32nd Street. The temporary closure is to prevent unsafe weaving from merging drivers.

Additional information is available on ramp closures and local street closures anticipated throughout the rest of the year. 

Staying Informed

Project information and updates can be found at I65CentralCorridor.com. While on the site, users can sign up to have project and traffic updates delivered to their inboxes or by text to their phones. Project updates are shared on KYTC District 5 (D5) Facebook and X pages.

Learn More

More Traffic Alerts

Reminder: Gray Street under I-65 to Temporarily Close on Monday

Chestnut Street under I-65 to close in mid-October As progress continues…

Broadway under I-65 to Reopen Early; Jacob Street to Close

Gray Street to temporarily close under I-65 in early October Work…

Gray Street to Temporarily Close Under I-65 in Early October

Jacob Street will permanently close when Broadway repens As progress continues…